Plan on 12–18 months from the start of the feasibility study through the end of active solicitations, with pledge redemption continuing for three to five years after that.
| Stage | Typical duration |
|---|---|
| Strategic planning and project definition | 6–12 months before any campaign activity |
| Phase I — Exploration, Discovery, Feasibility | 4–6 months |
| Phase II — Campaign Organization | 2–3 months |
| Phase III — Silent / Pacesetter Phase | 4–6 months |
| Phase IV — Public Phase | 2–3 months |
| Phase V — Operation Homestretch | 3–4 months |